358 fence packing affects more than the appearance of a shipment. Dense mesh panels, long posts, fixing bars and small hardware must arrive as an identifiable system that can be unloaded and installed. A low panel price loses its value if coatings are rubbed through, package marks are unclear or essential fittings are missing.
This guide uses the supplied packing and container photographs to explain what a buyer should agree before production. It covers commercial scope, package design, load planning and receiving checks. Begin with the selected 358 security fence configuration; its actual dimensions and component quantities determine the delivery plan.
On this page

1. Confirm what one quoted set contains
Ask whether the quotation covers panels only, panels with intermediate posts, or a complete schedule including corners, ends, gates and accessories. “One set” is not a universal unit. Its contents should be listed before prices are compared.
For example, a supplier may quote one panel and one line post as a repeating unit, while an isolated run still needs an additional end support. Gates and corners can change the post count and fixing arrangement. Use the actual layout to establish quantities instead of multiplying the total length by a simplified set definition.
| Supply group | Items to identify |
|---|---|
| Panels | Type, height, width, wire selection, finish and quantity by code |
| Posts | Intermediate, end, corner and special supports, with mounting detail |
| Fixings | Bars or clips, full bolt assemblies, caps and agreed spares |
| Gates and accessories | Separate assemblies and the exact included hardware |
| Packing and delivery | Protection, package marks, loading scope and named delivery place |
Use the posts and fixings guide to build the hardware schedule. Small components deserve the same item identification as the large steel parts.
2. Design panel bundles around the selected profile
Flat panels and bent panels do not stack in exactly the same way. A bent profile creates contact points and voids that affect bundle depth and the distribution of pressure. Specify how panels are arranged, separated and supported so the packing does not damage the profile or finish.
The package needs suitable support under the panel stack and protection where straps contact it. Strapping should hold the package together without concentrating load on unprotected coated wires. Edge and corner protection should remain in place during handling.
Agree the quantity per package together with dimensions, gross weight and the intended unloading equipment. The most densely packed bundle is not automatically the best choice for a site with limited lifting capacity or restricted access. Package size should work at both the loading and receiving ends.
Confirm whether panels of different heights or profiles can share a package. If mixed packing is necessary, the contents should remain traceable and accessible in the intended installation sequence. Avoid hiding small special panels beneath several unrelated bundles without documenting their location.
3. Protect posts and long fixing bars
Posts can damage each other when their corners or base plates rub during transport. The supplied photographs show wrapped posts and protected bundles. Define the contact protection and bundle restraint for the actual post shape, especially where welded plates or extensions create projections.

Keep the identification visible after wrapping. Mark post type, length and quantity on the package, and connect that mark to the packing list. An installer should not need to unwrap every bundle to distinguish intermediate posts from corner or gate supports.
Fixing bars need protection against bending and finish damage. Pack them in identified bundles that can be handled without losing individual pieces. Where bars look similar but have different hole positions, use separate item codes and clear labels.
4. Count hardware and include agreed spares
Pack bolts, nuts, washers, clips and caps by their actual assembly or item code. State quantities per bag or carton and total quantities in the packing list. If a fixing uses several small parts, show the complete assembly so one missing washer type is not overlooked.
Keep hardware cartons protected and located so they can be found during receiving. A carton marked only “accessories” is less useful than a label identifying the order, item codes and quantities. Photograph the counted contents before sealing when that forms part of the agreed inspection plan.
Agree spare quantities before shipment. Do not assume spare fasteners are included in a standard panel price. Replacing a small missing component internationally can be inconvenient, but adding uncontrolled extra parts can also create confusion; list spares as their own line.
5. Calculate container quantity from the complete load
A reliable loading estimate needs panel package dimensions, gross weights, post bundles, accessory cartons and any gates. It also needs the selected container and applicable transport limits. Neither panel count alone nor a photograph of a previous shipment establishes the quantity for a new order.
Check both space and weight. A load may reach a practical payload or handling limit before the volume is filled, while an awkward package shape can leave unused space. Consider access through the container doors and the order in which packages will be loaded and removed.

As a simple planning example, assume a quoted order contains 80 packages of panels, 12 post bundles and 4 hardware cartons. A load plan must account for all 96 packages, their individual weights and dimensions, and the way they can be restrained and unloaded. This example is a counting exercise, not a container-capacity promise.
The IMO/ILO/UNECE CTU Code provides global practice guidance for packing and securing cargo transport units. The responsible packer should use an appropriate loading and securing plan for the actual cargo and transport chain.
Ask for a preliminary load plan with the quotation when freight efficiency is important, then update it after package dimensions and weights are confirmed. A change in panel height, bend profile or post length can require a revised plan.
6. Define delivery terms and cost boundaries
Record the agreed delivery term, named port or place, and the responsibilities included in the price. Panel price, packing, inland transport, ocean freight, destination handling and final delivery are separate cost components unless the quotation explicitly includes them.
Compare offers on the same scope. A lower goods price may exclude posts, packing or a transport leg included elsewhere. The 358 fence price guide explains how to compare quotations without confusing panel cost with the total installed or landed cost.
Confirm production timing, inspection timing and booking arrangements together. A shipment should not be booked on the assumption that outstanding drawing approvals or inspection issues will resolve themselves. Keep the required destination and unloading date visible when planning the order.
7. Align documents with the packed goods
The commercial invoice, packing list and shipping instructions should use consistent product descriptions, quantities and parties. Include the package marks that appear on the goods. Where a shipment contains multiple sizes or finishes, the packing list should let the receiver identify each group.
Provide the information your appointed forwarder and destination customs specialist need to determine the applicable classification and import documentation. Do not copy a tariff code or duty assumption from a different fence shipment without checking the actual goods and destination requirements.
| Document or record | What to reconcile |
|---|---|
| Approved drawing and bill of materials | Manufactured configuration and quantities |
| Inspection release | Accepted items and closed nonconformities |
| Packing list | Package marks, contents, dimensions and weights |
| Commercial invoice | Agreed goods description, value and commercial scope |
| Shipping instructions | Consignee details, route and document requirements |
| Load photographs | Package condition, arrangement and shipment identification |
If timber packing is proposed, ask the freight and import team to confirm the applicable packaging requirements for the destination before packing begins. The selected packing material should be documented so a last-minute change does not disrupt the shipment.
8. Inspect before the container is closed
Complete the agreed product inspection before packed goods become inaccessible. Check the panel and post quantities, hardware totals, package labels and protection. Record the loading sequence and representative condition of the packages.
Resolve nonconformities before release. A photograph of a closed container cannot demonstrate that every required fixing is inside. The release decision should be supported by the packing and inspection records, not simply by evidence that loading occurred.
For measurable product checks, use the 358 fence quality inspection guide. The packing review complements those checks rather than replacing them.
9. Prepare the receiver before arrival
Send the package schedule and unloading information to the receiving team in advance. Confirm that the available equipment, access and storage area suit the package sizes and weights. Plan safe unloading with the responsible logistics team rather than improvising once the doors are opened.
At receipt, compare package marks and quantities with the packing list. Photograph visible damage before it is obscured by unpacking, and record affected item codes. Retain relevant packaging and records while the issue is assessed.
Store components in a stable, protected arrangement that preserves labels and prevents avoidable finish damage. Separate parts by installation sequence when practical. Give the installer the approved drawings and component schedule so the shipment can move from storage to the correct fence run without repeated sorting.
358 fence packing and importing questions
How many 358 fence sets fit in a 40-foot container?
It depends on panel dimensions, wire and profile, post and gate quantities, packing and transport limits. Request a load plan for the actual bill of materials.
Are posts included in a panel quotation?
Only if they are explicitly listed. Confirm the contents of a set and the separate quantities for ends, corners and gates.
Can flat and bent panels use the same packing plan?
Not automatically. Their stacking geometry and contact points differ, so package dimensions and protection should be checked for each profile.
What should the buyer check first on arrival?
Package identity, quantity and visible condition, using the packing list and pre-shipment records before detailed unpacking.