Stucco lath installation is easiest to inspect while you can still see the metal, fastening points and drainage details. Once the scratch coat goes on, a finished face cannot tell a distributor whether the correct sheet arrived, or tell an inspector where the fasteners landed. The following seven checks cover a framed exterior wall receiving Portland cement plaster. Each check identifies something worth recording before the next trade covers it.
On this page
1. Match the bundle to the stucco lath installation detail
Begin the stucco lath inspection by reading the approved wall section and the bundle label side by side. Record the sheet profile, weight per square yard, coating, backing, lot identification and wall location. Keep a labeled offcut from the first bundle when several profiles are on site. A flat and a self-furring sheet can have the same weight. Specify who will confirm any substitution while the bundle is still intact.
In the project’s referenced editions, ASTM C1063 addresses lathing and furring installation and ASTM C926 addresses application of the cement plaster. The distinction matters when a question concerns attachment rather than mortar. See the scope of ASTM C1063 and ASTM C926.

2. Trace the drainage path at one complete opening
On the approved window detail, follow water from the head flashing down to the point where it can exit. Then trace the same route on the wall. Compare how the water-resistive barrier (WRB) meets each flashing, penetration and lower termination. A corner photograph taken before lathing may show a reverse lap that would disappear behind the mesh. Use the required layer arrangement for the project’s sheathing and climate.
3. Check the marks on the first sheet
Mark the framing direction on the inspection photograph, then identify the sheet’s long dimension, its face and the location of any dimples or grooves. Common framed-wall details run the sheet’s long dimension across the supports. Follow the labeled product and approved detail for face and furring orientation. The direction the diamonds appear to point in a photograph alone does not settle all three questions.
Look across the first installed area at a low angle. Where the specified profile creates stand-off, overdriven fasteners or flattened dimples can pull the strands tight to the backing. Note that finding on the stucco lath inspection record. Flag the affected area before plastering, when the installer can still inspect the profile directly.


4. Measure metal lath overlap at a side, an end and a corner
Measure a long-edge lap and a short-end lap separately. As an example, the Florida Lath & Plaster Bureau’s framed-wall checklist gives ½ inch for side laps and 1 inch for end laps for the metal lath in its detail. It also calls for staggered end joints. Other plaster bases or approved assemblies can call for different laps. Compare your measurements with the job drawings and the specified edition. Florida Lath & Plaster Bureau lathing checklist (PDF).
At an inside corner, identify the corner reinforcement or wrap on the detail and check where the sheet ends land relative to the corner. Where paper is attached, check that the metal layers engage at the lap and the backing overlaps in drainage order. A wrinkle that puts paper between two mesh edges can escape a quick face-on inspection.
5. Trace stucco lath fasteners back to their support
Use framing marks to trace several fasteners, then compare fastener type, size, corrosion protection, spacing and engagement with the attachment schedule. Inspect a representative connection where the support can be identified. Photograph the stucco lath fasteners alongside a marked framing line so the installation record shows what they engage. A neat row seen from the front can still miss its stud. For a wall with exterior insulation, include the insulation thickness and the designed attachment through it in the review.
6. Walk the joints and terminations
Start at the weep screed, work up to a window return and finish at one movement joint. Identify where water exits, where an accessory terminates the plaster and where the wall design accommodates movement. A stucco lath installation can look continuous across the whole elevation while concealing a joint that should remain free. Check whether the approved joint detail requires the metal to stop. Mark each location on the elevation so it can be found again after plastering.
7. Record the items that the scratch coat will hide
| Save with the inspection record | Include in the photograph or note |
|---|---|
| Bundle and first installed sheet | Bundle tag, installation area, date and approved product identifier |
| Two representative seams | Scale across each lap, with enough surrounding wall to identify the seam direction |
| One opening and one termination | WRB, flashing sequence, accessory and drainage exit before concealment |
| An unresolved detail | Marked location, drawing reference, responsible reviewer and correction before cover |
Stucco lath installation questions from the field
What size staples should we buy for stucco lath installation?
Start with the attachment schedule for the actual wall. It identifies whether staples are allowed and the required crown, leg length, spacing, penetration and corrosion protection. Sheathing thickness changes how much leg length reaches wood framing. A staple size quoted for a wood-framed wall cannot simply be carried to steel framing or concrete.
Can we attach metal lath directly to plywood?
Plywood identifies the sheathing, while the wall detail identifies the required anchorage. Where the detail calls for framing attachment, fastening only to the panel misses the specified support. For an alternative attachment system, obtain the evaluated detail and its limits before ordering fasteners.
If your question begins at the supply counter, send the wall section and the bundle description with your request for galvanized diamond lath. The plaster base comparison can help identify whether the site photograph shows expanded sheet, rib lath or a wire base.